Another important date was
9 June 1975, when a high level delegation from SASOL (De Witt and Coetzee),
accompanied by their consultant (Heyns and van Niekerk) came to see me in my
office. They wanted to know from which dam they could start their pipeline to
supply the proposed new SASOL II plant on the Eastern Highveld of the then
Transvaal. I replied that things were not so simple: that we had various other
customers in the area such as the existing and proposed new coal-fired Escom
power stations, coal mines, municipalities and other industries. The delegation
was clearly not at all pleased with my reply and went higher-up, to no avail.
This was the start of a major planning study which lead to the construction of
the Grootdraai dam in the Vaal River near Standerton. Although there was no
capacity in the river to meet their demand, it was considered that, because of
the urgency of SASOL, water could be “borrowed” from the Vaal as backed up by
the Tugela, while further resources to supply the area could be implemented. Little
more than four years were available for planning, designing, constructing and
commissioning of the major water supply project that would be needed. Any delay
would cost SASOL millions in interest every month. A pumping station and canal
would take the Grootdraai water to the continental watershed between the Vaal-
and Olifants basins and from there to the plant and also into the
Trichardsfontein balancing dam feeding a tributary of the Olifants to the Matla
and Duvha power stations. A further
power station, called Ilanga was also already on the drawing board.
At this stage a broader
picture of the water supply position on the Highveld is necessary. At the time
when Escom was planning the Komati power station, it was found that the
relatively large amount of water needed could not be met from local resources
such as the Olifants River. The two under-used and water-rich rivers of the
Eastern Transvaal, the Komati and the Usutu were identified as possible sources
and the Nooitgedacht Dam on the Upper Komati was completed in 1962. The next
power station to be erected in the area was Camden, supplied with water from
the Jericho Dam in the Usutu basin, completed in 1968. In the early seventies
another three power stations were erected on the Highveld viz. Arnot, Hendrina
and Kriel. The Vygeboom Dam on the Komati River was completed by the Department
in 1971 to supply the two former stations. But there was a shortfall for Kriel. The next step was the construction of the Westoe
dam on the Usutu, which was completed in 1972 and was raised a few years later.
A further dam on the Ngwempisi branch of the Usutu, called Morgenstond was
completed in 1978. A pipeline connection between Camden and Kriel allowed the
latter power station to be supplied with Usutu water. The next step was to
supply water to the Matla and Duvha power stations. From the Usutu Government
Water Scheme, there was still some water available to feed the initial needs of
Matla. At the same time there was still some water available from the Komati to
meet the initial needs of Duvha. At first it was considered to meet the
remaining requirements of Matla and Duvha by further dams in the Usutu and the
Komati respectively. Storage would be provided on the Olifants River, to be
filled by the extra capacity of the supply pipelines during off-peak times. The
proposed dam could then also hold a strategic reserve. This proposal bore the
name of Komati-Usutu link system.
After this historic
digression, it is now back to Grootdraai. The water “borrowed” from the Vaal is
to be replaced by transfers from the Usutu and therefore the project was called
the first phase of the Usutu-Vaal project, but is, in fact, a Vaal-Olifants
link. The replacement water comes from the Assegaai branch of the Usutu at the
Heyeshope site via the Usutu-Vaal inter basin transfer. Originally, DWA
investigated a site in a gorge a few kilometres downstream of Heyeshope. When I
drew a long section of the river bed, I found that this site needed an unnecessary
high dam to command the basin, and as a result located Heyeshope as a far more
economic site, notwithstanding the required length of the dam. Because of the
flexibility of supply from different sources to the various power stations the
supply network was now called the Komati-Usutu link system. In writing this
text, my memory was assisted by a paper I submitted to the United Nations Water
Conference in Mar del Plata, Argentina in March 1977. (At the last moment the
SA delegation was barred from the Conference!) The paper was called: “Inter
basin water transfers in South Africa”.
Another water supply
project to an Escom power station that I was involved with was the Zaaihoek Dam
on the Slang River, a tributary of the Buffalo River, in turn a tributary to
the Tugela. It supplies water to the Majuba power station and can also
supplement the resources of the Vaal River, because the scheme is an
inter-basin transfer.
No comments:
Post a Comment