Annexure

SETTING OUT STOMPDRIFT DAM

I accurately measured a base line by tape, and established a series of setting-out points by triangulation. With the aid of an electric Olivetti Divisuma calculator, I calculated the co-ordinates of the upstream and downstream intersections of the joints with the intrados and extrados of the arches at the various pouring levels, as well as the exact centre of the extrados. This was before the advent of computers, and was a very laborious calculating task, involving the solutions of thousands of quadratic equations. In addition I calculated the co-ordinates of the intersection of two lines: the line from the left hand extrados intersection to the right hand intrados intersection and the line from the right hand extrados intersection to the left hand intrados intersection. To establish this point of intersection on the concrete of a previously cast box, angles were calculated from three of the setting-out beacons. The surveyor’s assistant – Elias, whom I brought along from Ebenezer, had a tripod fitted with an optical plumb bob. He was directed by me from the one beacon to mark two points along the calculated line, and mark that line by pencil on the concrete. I then set up on the second beacon, to enable the assistant to mark the intersection. I then went on the box with my tachy, orientated towards the beacons I had used, and checked whether I was on the correct position by pointing to a third beacon, thus not only checking the setting out, but also the triangulation calculations. After that, I had the assistant marking the direction of the lines towards the four corners of the box and to the centre of the extrados, which also had been previously calculated. The corner points themselves could not be marked directly, because three of the four corners were then in mid-air, because of the overhang of the arch, as well as the joints. The carpenters were supplied with a drawing showing the calculated distances from the setting-out point to the corners and the centre of the extrados, as well as the calculated offset at the centre of the extrados and other calculated dimensions, such as the thickness. These enabled the carpenters to check their work, as well as my own work, because any error would be shown, whatever its source. As can be imagined, all these calculations were very laborious indeed, and took up many man-months of high-level staff. Later, when I was transferred to head-office, I attended a computer programming course from IBM. As a practical problem, I calculated all these data for the Kat River Dam, then under construction, which greatly facilitated things there. Also attached are the instructions I drew up for that purpose.SETTING OUT STOMPDRIFT DAM
I accurately measured a base line by tape, and established a series of setting-out points by triangulation. With the aid of an electric Olivetti Divisuma calculator, I calculated the co-ordinates of the upstream and downstream intersections of the joints with the intrados and extrados of the arches at the various pouring levels, as well as the exact centre of the extrados. This was before the advent of computers, and was a very laborious calculating task, involving the solutions of thousands of quadratic equations. In addition I calculated the co-ordinates of the intersection of two lines: the line from the left hand extrados intersection to the right hand intrados intersection and the line from the right hand extrados intersection to the left hand intrados intersection. To establish this point of intersection on the concrete of a previously cast box, angles were calculated from three of the setting-out beacons. The surveyor’s assistant – Elias, whom I brought along from Ebenezer, had a tripod fitted with an optical plumb bob. He was directed by me from the one beacon to mark two points along the calculated line, and mark that line by pencil on the concrete. I then set up on the second beacon, to enable the assistant to mark the intersection. I then went on the box with my tachy, orientated towards the beacons I had used, and checked whether I was on the correct position by pointing to a third beacon, thus not only checking the setting out, but also the triangulation calculations. After that, I had the assistant marking the direction of the lines towards the four corners of the box and to the centre of the extrados, which also had been previously calculated. The corner points themselves could not be marked directly, because three of the four corners were then in mid-air, because of the overhang of the arch, as well as the joints. The carpenters were supplied with a drawing showing the calculated distances from the setting-out point to the corners and the centre of the extrados, as well as the calculated offset at the centre of the extrados and other calculated dimensions, such as the thickness. These enabled the carpenters to check their work, as well as my own work, because any error would be shown, whatever its source. As can be imagined, all these calculations were very laborious indeed, and took up many man-months of high-level staff. Later, when I was transferred to head-office, I attended a computer programming course from IBM. As a practical problem, I calculated all these data for the Kat River Dam, then under construction, which greatly facilitated things there. Also attached are the instructions I drew up for that purpose.SETTING OUT STOMPDRIFT DAM
I accurately measured a base line by tape, and established a series of setting-out points by triangulation. With the aid of an electric Olivetti Divisuma calculator, I calculated the co-ordinates of the upstream and downstream intersections of the joints with the intrados and extrados of the arches at the various pouring levels, as well as the exact centre of the extrados. This was before the advent of computers, and was a very laborious calculating task, involving the solutions of thousands of quadratic equations. In addition I calculated the co-ordinates of the intersection of two lines: the line from the left hand extrados intersection to the right hand intrados intersection and the line from the right hand extrados intersection to the left hand intrados intersection. To establish this point of intersection on the concrete of a previously cast box, angles were calculated from three of the setting-out beacons. The surveyor’s assistant – Elias, whom I brought along from Ebenezer, had a tripod fitted with an optical plumb bob. He was directed by me from the one beacon to mark two points along the calculated line, and mark that line by pencil on the concrete. I then set up on the second beacon, to enable the assistant to mark the intersection. I then went on the box with my tachy, orientated towards the beacons I had used, and checked whether I was on the correct position by pointing to a third beacon, thus not only checking the setting out, but also the triangulation calculations. After that, I had the assistant marking the direction of the lines towards the four corners of the box and to the centre of the extrados, which also had been previously calculated. The corner points themselves could not be marked directly, because three of the four corners were then in mid-air, because of the overhang of the arch, as well as the joints. The carpenters were supplied with a drawing showing the calculated distances from the setting-out point to the corners and the centre of the extrados, as well as the calculated offset at the centre of the extrados and other calculated dimensions, such as the thickness. These enabled the carpenters to check their work, as well as my own work, because any error would be shown, whatever its source. As can be imagined, all these calculations were very laborious indeed, and took up many man-months of high-level staff. Later, when I was transferred to head-office, I attended a computer programming course from IBM. As a practical problem, I calculated all these data for the Kat River Dam, then under construction, which greatly facilitated things there. Also attached are the instructions I drew up for that purpose.SETTING OUT STOMPDRIFT DAM
I accurately measured a base line by tape, and established a series of setting-out points by triangulation. With the aid of an electric Olivetti Divisuma calculator, I calculated the co-ordinates of the upstream and downstream intersections of the joints with the intrados and extrados of the arches at the various pouring levels, as well as the exact centre of the extrados. This was before the advent of computers, and was a very laborious calculating task, involving the solutions of thousands of quadratic equations. In addition I calculated the co-ordinates of the intersection of two lines: the line from the left hand extrados intersection to the right hand intrados intersection and the line from the right hand extrados intersection to the left hand intrados intersection. To establish this point of intersection on the concrete of a previously cast box, angles were calculated from three of the setting-out beacons. The surveyor’s assistant – Elias, whom I brought along from Ebenezer, had a tripod fitted with an optical plumb bob. He was directed by me from the one beacon to mark two points along the calculated line, and mark that line by pencil on the concrete. I then set up on the second beacon, to enable the assistant to mark the intersection. I then went on the box with my tachy, orientated towards the beacons I had used, and checked whether I was on the correct position by pointing to a third beacon, thus not only checking the setting out, but also the triangulation calculations. After that, I had the assistant marking the direction of the lines towards the four corners of the box and to the centre of the extrados, which also had been previously calculated. The corner points themselves could not be marked directly, because three of the four corners were then in mid-air, because of the overhang of the arch, as well as the joints. The carpenters were supplied with a drawing showing the calculated distances from the setting-out point to the corners and the centre of the extrados, as well as the calculated offset at the centre of the extrados and other calculated dimensions, such as the thickness. These enabled the carpenters to check their work, as well as my own work, because any error would be shown, whatever its source. As can be imagined, all these calculations were very laborious indeed, and took up many man-months of high-level staff. Later, when I was transferred to head-office, I attended a computer programming course from IBM. As a practical problem, I calculated all these data for the Kat River Dam, then under construction, which greatly facilitated things there. Also attached are the instructions I drew up for that purpose.




















No comments:

Post a Comment